PNWCarbonRemoval

Under Development

Project Operator: CarbonQuest, Inc.

Team: Shane Johnson, Brian Asparro, Anna Pavlova

Location: Spokane

Biogenic Co2 from a waste-to-energy facility in Eastern Washington state of the US. The offtake option under development would be sequestration at a localized onsite sequestration well (pending geological testing) or at another sequestration site within the region. Initial project will remove 110,000 tons of CO2 annually, with a ramp-up to 280,000 tons per year in 3 years after the start of project. The project meets additionality requirements for carbon credit markets and will be registered with one of the leading registries. Currently the developed received funding for a full engineering feasibility study and has identified partners for local sequestration testing. The developer has commercial experience with the type of equipment at the facility. If sequestration locally is found unsuitable, the CO2 can be sold into the e-fuel or petroleum displacing products or transported by rail to another sequestration site. These backup options also have potential offtake partners already identified.
Registry
American Carbon Registry
Methodology
Carbon Capture and Storage Projects
Expected Annual Credit Quantity
110,000
Project Emissions Source
Solid Waste, Incineration
Type Of Well For Sequestration
Class VI
Project's Financial Additionality
There may be some state funding for the project, but not enough to make it financially feasible by itself
Additionality
Sequestering CO2 is expensive. The project needs a robust carbon credit to make it financially viable when accounting for transportation and sequestration of the Captured Co2.
Expected Project FID
2/28/2025
Expected Credit Issuance Date
07/01/2026